Door Schedules for Hotel Projects: How to Build One That a Factory Can Price Accurately

A door schedule for a hotel project is the single document that decides whether a quotation is precise or full of assumptions. This guide lists the columns a factory needs and how to fill them.

A well-built door schedule for a hotel project is the fastest way to get a quotation that reflects what you actually want. When a schedule is vague, the factory has to fill the gaps with assumptions about size, core, finish and hardware preparation, and those assumptions rarely match your intent. This guide shows which columns a schedule needs and how to complete them so the price comes back clean.

Why the schedule matters more than the drawings

Architectural plans show where doors sit, but they seldom carry every detail a factory needs to price and manufacture them. The schedule is where openings, door types, dimensions and specifications are gathered in one place, one row per opening or per group of identical openings.

A factory estimator works from this table. Every blank cell becomes either a question, a delay or a line in the quotation that reads "assumed". Filling the cells yourself keeps control of the specification in your hands.

The core columns every door schedule needs

Think of the columns in three groups: identification, geometry and specification. If you use a door schedule template from your design team, check it against the lists below before sending it out.

Identification columns

  • Door mark or ID: a unique reference such as D01 or R-101-A that will also appear on drawings and packing labels.
  • Location: floor, room type or zone, for example guest room entrance, bathroom, wardrobe, corridor, back-of-house.
  • Door type code: links the row to the door types list, which holds the design details described below.
  • Quantity: the number of identical leaves, kept consistent with your door quantity takeoff.

Geometry columns

  • Leaf width, height and thickness: in millimetres first, with imperial in brackets if the project uses it, for example 900 x 2100 x 45 mm (35.4 x 82.7 x 1.8 in).
  • Structural opening or wall opening size: so the factory can check clearances against the leaf size.
  • Number of leaves: single, double or unequal leaf.
  • Handing and swing: left or right hand, inward or outward, ideally with a clear convention noted on the schedule.
  • Wall thickness or jamb depth: essential if frames are in the supply scope.

Specification columns

  • Door model or design: flush, grooved, panelled, glazed or another reference from the catalogue or your drawings.
  • Core: solid timber, particleboard, honeycomb or mineral core, depending on weight, acoustic and fire needs.
  • Surface and finish: veneer species, HPL, lacquer or paint colour with a RAL or other reference, plus the sheen level.
  • Fire rating: required duration and the standard applied in the destination country, or "none".
  • Acoustic requirement: target Rw value, if any, and whether seals and drop bottoms are needed.
  • Glazing: glass type, size and position, where relevant.

Hardware and preparation columns

Hardware is where most hidden assumptions live. Even if the factory is not supplying the ironmongery, it must know what to machine into the leaf and frame.

  • Hinges: type, quantity and position.
  • Lock type and preparation: mortice, electronic or card lock, with the supplier's template or cut-out drawing.
  • Closer, stop and other fittings: whether prepared only or supplied.
  • Peephole, signage or other cut-outs: height and position.
  • Supply scope for hardware: supplied by the factory, by the client or by a third-party supplier.

A simple "hardware by others, prepared by factory" note can change both price and schedule, so state it for each door type.

Frame, installation and logistics columns

If the frame is part of the order, give it its own set of fields: material, profile, rebate or stop detail, architrave and finish. If doors are supplied as leaves only, mark that clearly so no frame cost is expected or omitted.

Add a few fields for delivery planning as well:

  • Delivery phase or floor: helps the factory sequence production and packing.
  • Installation scope: supply only, or supply and on-site installation.
  • Special remarks: anything unusual, such as tall leaves, heavy weights or curved tops.

A sample layout you can adapt

The table below is a condensed example of how a row can look. Your own schedule will have more columns, but the logic stays the same.

MarkLocationTypeSize (mm)QtyCore and finishRatingHardware prep
D01Guest room entranceT1 flush900 x 2100 x 45Per takeoffParticleboard core, veneer, matt lacquerFire and acoustic as specifiedElectronic lock, closer, peephole
D02BathroomT2 moisture-resistant800 x 2100 x 40Per takeoffMoisture-resistant core, sealed edges, paintNoneMortice lock, hinges
D03WardrobeT3 slattedPer openingPer takeoffSolid frame, paintedNoneMagnetic catch, pull

The quantities and sizes above are placeholders to show structure, not recommendations. Your standards and room layouts decide the real values.

Building the door types list

The door types list is a companion to the schedule. Each type code, such as T1 or T2, has its own sheet or description with an elevation, a section through the leaf and edge, the core, the finish and the hardware positions.

This separation keeps the schedule short. Instead of repeating a long specification in every row, you refer to the type code, and the details live in one place where they are easy to update.

How to do the door quantity takeoff

A reliable door quantity takeoff starts from floor plans, not from the room count alone. Count every opening by type: room entrances, bathrooms, wardrobes, connecting doors, corridor fire doors, service and back-of-house doors, and public area doors.

Then reconcile the numbers. Check the total against the room schedule, the number of floors and any repeated typical floors. Allow for a clearly stated spare quantity if the owner wants spares, and show it as a separate line rather than burying it in the main count.

Common mistakes that cause assumptions in quotations

  • Mixed units: metric and imperial in the same column without a note.
  • Missing handing: the factory cannot machine hinges and locks without it.
  • No fire or acoustic data: doors are priced as standard, then re-priced later.
  • Unclear supply scope: frames, hardware or installation assumed by one party and excluded by the other.
  • Finish described only by name: "walnut" or "grey" without a sample, code or reference.
  • Outdated revisions: schedule and drawings that no longer match, with no revision date.

Before you send the schedule

Run through a short checklist:

  1. Every row has a unique mark and a type code.
  2. Sizes, thickness and handing are complete and units are consistent.
  3. Core, finish, fire and acoustic requirements are filled in or marked as none.
  4. Hardware supply scope and preparation details are stated per type.
  5. Frame, installation and delivery phasing are defined.
  6. The file carries a revision number and date, and is sent with the plans and type sheets.

Send the schedule in an editable format such as a spreadsheet, together with a PDF of the same revision, so the estimator can sort, filter and check totals while keeping a fixed reference copy.

Final thoughts

A complete schedule shortens the quotation cycle, makes offers from different factories comparable and prevents disputes about what was included. It also becomes the backbone of production, packing and installation later on.

If you are preparing a hotel project, send us your draft door schedule, plans or even a rough room list. We will review it, point out missing columns and come back with a quotation based on your specification rather than on our assumptions.

Sıkça Sorulan Sorular

What is a door schedule in a hotel project?

A door schedule is a table listing every door opening in the project with its mark, location, quantity, size, handing, core, finish, rating and hardware preparation. It lets a factory price and manufacture doors accurately, and it becomes the reference for packing and installation.

What information does a factory need to price hotel doors?

At minimum: quantities by type, leaf size and thickness, handing, door model, core, finish reference, fire and acoustic requirements, hardware preparation and supply scope. Add frame details, installation scope and delivery phasing so the quotation does not rely on assumptions.

Should I send a door schedule or drawings for a quotation?

Send both if you can. Drawings show design and placement, while the schedule gives the structured data an estimator needs. Include type sheets with elevations and sections, and make sure all documents carry the same revision number.

What is the difference between a door schedule and a door types list?

The schedule lists each opening or group of openings with its quantity and location. The door types list describes each design code in detail, with elevations, sections and specifications. The schedule refers to the type codes, which keeps it short and easy to update.

Can I use a standard door schedule template?

Yes, a template is a good starting point. Check it against your project and add any missing columns such as handing, fire rating, acoustic target, hardware preparation and supply scope. Templates often leave these out, and they are exactly where assumptions appear.

Every hotel project is different. Send us your drawings or room schedule for a tailored proposal on materials, lead time and shipping.