Wooden Door Budget Planning for a 100-Room Hotel: A Worked Example
A step-by-step worked example showing how to count doors by type and allocate cost shares for a 100-room hotel. Use it as a template for your own door budget.
A realistic door budget for a 100-room hotel starts with a count, not a price. Once you know how many leaves of each type the building needs, cost allocation becomes a matter of weighting, and the final estimate is far easier to defend. This guide walks through a worked example with illustrative quantities that you can replace with your own room schedule.
We deliberately do not quote unit prices here. Cost depends on materials, finish, hardware, fire rating, destination and shipping terms, so the example works in cost shares and cost drivers instead. Your factory quotation will supply the actual figures.
Step 1: Define the hotel in the example
Our example is a mid-scale city hotel with 100 keys, one lobby level with a restaurant and meeting room, and guest floors served by a central corridor. The assumptions below are for illustration only.
- 86 standard rooms, 10 family or connecting rooms and 4 suites.
- Every room has an entrance door, a bathroom door and a wardrobe opening.
- Connecting rooms are paired, so 5 pairs share a wall with a connecting door in each room.
- Back-of-house and public areas add a smaller group of service and fire-compartment doors.
Step 2: Count doors by type
Start with guest rooms, because they drive the quantity. Then add the remaining openings from the architect's door schedule.
| Door type | Basis of count | Illustrative quantity |
|---|---|---|
| Room entrance doors | 1 per key | 100 |
| Bathroom doors | 1 per key | 100 |
| Wardrobe doors | 1 opening per key, often two leaves | 100 openings (about 200 leaves if double) |
| Connecting doors | 2 leaves per connected pair, 5 pairs | 10 |
| Suite entrance doors (double-leaf) | 1 opening per suite | 4 |
| Suite internal doors | Bedroom and living area separation | 4 to 8 |
| Public area and meeting room doors | From architect's schedule | 10 to 15 |
| Back-of-house and service doors | From architect's schedule | 15 to 25 |
In this example, the project has roughly 240 to 260 door openings before wardrobe leaves are counted separately. That total is the number you must verify against the door schedule, because a missed group of openings is the most common reason a door cost estimate drifts later.
Add a spares allowance
Most buyers add a small allowance of extra leaves for damage in transit or on site, and for future replacements. The percentage is a commercial decision between you and the supplier. It is cheaper to make spares in the same production run than to reorder years later and risk a finish mismatch.
Step 3: Group doors into specification tiers
Not every door needs the same specification. Grouping them lets you spend where guests and inspectors will notice, and simplify where they will not.
- Tier A, high-visibility and performance doors: room entrance doors, which usually need fire performance, acoustic seals, lock preparation and a premium finish.
- Tier B, standard interior doors: bathroom and wardrobe doors, where moisture resistance and edge protection matter more than special performance.
- Tier C, statement doors: suite entrances, lobby and restaurant doors, often larger, with veneer matching or custom details.
- Tier D, utility doors: back-of-house and service doors, built for heavy traffic with simple finishes.
Step 4: Allocate cost shares, not just a total
Instead of guessing a single number, think about where the money is likely to go. In a typical hotel of this size, the room entrance doors form the largest single block because of their quantity and the performance features they carry. Bathroom and wardrobe doors follow, with their cost depending on whether you choose hinged, sliding or pocket solutions.
Statement doors are few in number but can take a disproportionate share per leaf. Utility doors are the easiest place to hold costs down. The exact percentages vary by project, so build them from your own quotation lines rather than from a rule of thumb.
What sits inside a door cost
When you compare offers, make sure each of these items is visible, or clearly excluded:
- Leaf: core, facings, edge banding and finish.
- Frame or lining, with architraves where required.
- Hardware: hinges, locks, closers, stops and seals, whether supplied by the factory or by others.
- Fire and acoustic testing documentation, where the tender calls for it.
- Packing, export documents and shipping under your chosen Incoterm.
- Installation, if you want the factory team on site.
Step 5: Understand the cost drivers
Several decisions move a door cost estimate more than any others. Review them before you finalise the budget.
- Fire rating: fire-rated leaves require certified construction, special frames and intumescent seals, which affects both price and lead time.
- Finish: veneer, lacquer, HPL and painted MDF carry different material and labour costs. Matching to RAL or a sample adds approval steps.
- Core and thickness: heavier cores and thicker leaves improve feel and acoustics but increase material and freight weight.
- Custom sizes and profiles: non-standard heights, grooves or panelled designs need extra programming and handling.
- Hardware preparation: electronic lock routing, cable paths and peepholes add machining time.
- Order structure: higher repeat quantities of the same model are usually easier to optimise than many one-off designs.
Step 6: Add logistics and installation to the budget
Door cost estimates often stop at the factory gate, but the budget should not. Include packing, container space and freight to your port or site. Compare terms such as FOB, CIF or DAP on a like-for-like basis, because they place different costs and risks on you.
If installation is part of the scope, allow for frame fixing, hanging and final adjustment. Delivering by floor and room type helps the fit-out team work in sequence and reduces handling damage.
Step 7: Keep a contingency and a value engineering list
No door budget is final until drawings, samples and hardware are approved. Hold a contingency for changes in the design, finish or hardware, and agree in advance who owns it.
It also helps to prepare a short list of savings options that do not change the look, for example simplifying finishes on utility doors, standardising door sizes across room types or reducing the number of unique models. Decide these early, not after production has started.
A simple budgeting checklist
- Extract every opening from the architect's door schedule and reconcile it with the room schedule.
- Group the openings into specification tiers.
- Define fire, acoustic, moisture and hardware requirements for each tier.
- Request itemised quotations on the same basis from each supplier.
- Add packing, freight, customs and installation as separate lines.
- Add spares and a project contingency.
- Review the total against your overall FF&E budget and adjust by tier, not across the board.
Next step
If you are planning a 100-room hotel or a similar project, send us your door schedule or room schedule. We will review the quantities, suggest specification tiers and come back with an itemised quotation, lead time estimate and shipping options for your destination.
Sıkça Sorulan Sorular
How many doors does a 100-room hotel typically need?
It depends on the layout, but each key usually has an entrance door, a bathroom door and a wardrobe opening, which already gives about 300 openings or leaves. Suites, connecting rooms, public areas and back-of-house spaces add more. Always confirm the final count against the architect's door schedule.
What is the biggest cost driver in a hotel door budget?
Room entrance doors usually form the largest block because of their quantity and added features such as fire performance, acoustic seals and lock preparation. Finish, core type, custom sizes and shipping terms also move the total significantly, so review them early.
Should I include hardware in the door cost estimate?
Yes, either as a separate line or clearly marked as supplied by others. Hinges, locks, closers, stops and seals can be a notable share of the cost. Check that every quotation states what is included so you can compare offers fairly.
How many spare doors should I order?
There is no single rule. A small allowance for transit damage and future replacements is common, and the right amount depends on the project size, the finish and your maintenance plan. Making spares in the same production run helps keep colour and grain consistent.
Can I reduce the door budget without changing the design?
Often, yes. Standardising sizes across room types, limiting the number of unique models, simplifying finishes on back-of-house doors and planning hardware early can lower cost without visibly changing the guest experience. Agree these options before production begins.